Update Original Labor Hours Budget
Original Labor Hour Budgets can not be added or modified for the following scenarios.
- Workflow is turned on, an approval rule applies, and workflow has been initiated.
- Workflow is turned on, an approval rule applies, and transaction has been approved.
- Open an existing Prime Contract and scroll down to the Original Prime Contract Budgets section.
- Click the Labor Hours link. This will show cost codes and labor hour budgets in read only mode.
- Click Edit to enable changes.
- Navigate to a Job Cost Code that requires updating. If the Job Cost Code is not shown, see the next section on importing cost codes.
- Enter the budgeted hours.
- Repeat the last two steps for other Job Cost Codes that require updating.
- Click the Save button shown below the grid.
- Review subtotals at the bottom of the grid.
Import Job Cost Codes into the Labor Hour Budgets Table
- Click the Add/Import Items drop-down shown above and to the right of the Labor Hour Budgets grid.
- Click Import Job Cost Code in the drop-down. This will refresh the page and list all the Job Cost Codes for the selected Project.
- Select one or more Job Cost Codes using the checkbox shown on the left.
- Click the Add and Close button.