Convert work orders to prime invoices
Before you begin
- The prime contract type must be Cost Plus with or without GMP.
- The prime contract must be selected on the work order (WO).
- The WO status must be approved.
- The WO billable status must be billable.
- The WO issue and status dates must be earlier than the prime invoice's issue date.
- The estimated or actual values must be higher than zero.
- The WO must not have been previously invoiced.
Run the Work Order to Prime Invoice wizard
- Go to Projects and select the appropriate project in the Quick Select section.
- On the Project Home page, select Prime Invoices in the Client Contract Admin section.
- Select Actions > Add From WO.
- Optionally, update the Project number as needed.
- Select the Prime Contract.
- Select the Value To Use for the invoice item price: Actual or Estimated Sell Total.
- In the Work Orders section, select one or more WOs that will be included in the prime invoice.
- Select Next.
- Optionally, update the Invoice # as needed.
Sage Construction Management automatically assigns the next number in sequence, based on the existing records and the default format.
- Optionally, update the Order Number.
- Optionally, update the Issue Date.
The default value is today's date.
- Optionally, select the payment Terms.
Sage Construction Management automatically calculates the Payment Due Date according to the selected term’s text format.
- Optionally, update the Payment Due Date as needed.
- Optionally, select the Approved checkbox to set the prime invoice to approved.
If this checkbox is not selected, the prime invoice will remain in draft status.
- Optionally, clear the Use Default AR Tax Code or Tag Related Files checkboxes as needed.
- Select Finish.