Import committed and cost to date transactions in work orders
- Go to Projects and select the appropriate project in the Quick Select section.
-
On the Project Home page, select Work Orders in the Documentation section.
-
Select the work order number from the list.
-
In the Work Order Items section, select Add / Import Items, then select one of the following options:
Import Committed Cost Transactions-
Select Import Committed Cost Transactions.
-
Optionally, for labor or equipment timecards select the Include Comments checkbox as needed.
-
Select Import.
The following committed cost transactions that reference the CO will be imported:
- Purchase orders (POs)
- Bills not from POs
- Subcontracts
- SCOs
- Labor timecards
- Equipment timecards
- Miscellaneous expenses
Import Cost To Date Transactions-
Select Import Cost To DateTransactions.
-
Optionally, for labor or equipment timecards select the Include Comments checkbox as needed.
-
Select Import.
The following cost to date transactions that reference the CO will be imported:
- Bills
- Labor timecards
- Subcontracts
- Equipment timecards
- Miscellaneous expenses
-