Crew Example In Estimate Cost Database

Crew Description

Description Daily Production Prod. Units
Compaction Crew - Road Work 400 CY

Labor Components

Labor Description Quantity Hours
Labor Foreman 1 8.0
Laborer 1 8.0
Equipment Operator 3 8.0

Equipment Components

Equipment Description Quantity Hours
54" Smooth Drum Vibratory Roller 2 8.0
2200 Gallon Water Truck 1 8.0

Same Crew Example When Added To An Estimate

Crew Header

Estimate Assembly Description Units Formula
Compaction Crew - Road Work Days = (V02 / V01)

Formula Variables

Variable Variable Description Units
V01 Average Daily Production Quantity CY
V02 Total Quantity CY

Note: When Crews are added to an estimate, variables and formulas are auto-generated using the daily production quantity and number of workers and pieces of equipment.

Labor Components

Estimate Item Description Units Formula
Labor Foreman Days = (V02 / V01) * 1
Laborer Days = (V02 / V01) * 1
Equipment Operator Days = (V02 / V01) * 3

Note: "1" and "3" multipliers shown in formulas above indicate the number of workers. Average Work Hours are used in the Labor Conversion factor which is not shown here.

Equipment Components

Estimate Item Description Units Formula
54" Smooth Drum Vibratory Roller Days = (V02 / V01) * 2
2200 Gallon Water Truck Days = (V02 / V01) * 1

Note: "1" and "2" multipliers shown in formulas above indicate the pieces of equipment. Average Operating Hours are used in the Equipment Conversion factor which is not shown here.