Crew examples
Crew in the cost database
-
Crew description:
Description Daily production Production units Compaction crew - Road work 400 CY -
Labor components:
Labor description Quantity Hours Labor foreman 1 8.0 Laborer 1 8.0 Equipment operator 3 8.0 -
Equipment components:
Equipment description Quantity Hours 54" smooth drum vibratory roller 2 8.0 2200 gallon water truck 1 8.0
Crew in an estimate
-
Crew header:
Estimate assembly description Units Formula Compaction crew - Road work Days = (V02 / V01) -
Formula variables
Variable Variable description Units V01 Average daily production quantity CY V02 Total quantity CY When Crews are added to an estimate, variables and formulas are automatically generated based on the daily production quantity and the number of workers and equipment. -
Labor components
Estimate item description Units Formula Labor foreman Days = (V02 / V01) * 1 Laborer Days = (V02 / V01) * 1 Equipment operator Days = (V02 / V01) * 3 In the formulas above, the 1 and 3 multipliers indicate the number of workers. Average work hours are used to calculate the labor conversion factor, though that calculation is not shown here. -
Equipment components
Estimate item description Units Formula 54" smooth drum vibratory roller Days = (V02 / V01) * 2 2200 gallon water truck Days = (V02 / V01) * 1 In the formulas above, the 1 and 3 multipliers indicate the pieces of equipment. Average operating hours are used to calculate the equipment conversion factor, though that calculation is not shown here.