Crew Example In Estimate Cost Database
Crew Description
Description
|
Daily Production
|
Prod. Units
|
Compaction Crew - Road Work
|
400
|
CY
|
Labor Components
Labor Description
|
Quantity
|
Hours
|
Labor Foreman
|
1
|
8.0
|
Laborer
|
1
|
8.0
|
Equipment Operator
|
3
|
8.0
|
Equipment Components
Equipment Description
|
Quantity
|
Hours
|
54" Smooth Drum Vibratory Roller
|
2
|
8.0
|
2200 Gallon Water Truck
|
1
|
8.0
|
Same Crew Example When Added To An Estimate
Crew Header
Estimate Assembly Description
|
Units
|
Formula
|
Compaction Crew - Road Work
|
Days
|
= (V02 / V01)
|
Formula Variables
Variable
|
Variable Description
|
Units
|
V01
|
Average Daily Production Quantity
|
CY
|
V02
|
Total Quantity
|
CY
|
Note: When Crews are added to an estimate, variables and formulas are auto-generated using the daily production quantity and number of workers and pieces of equipment.
Labor Components
Estimate Item Description
|
Units
|
Formula
|
Labor Foreman
|
Days
|
= (V02 / V01) * 1
|
Laborer
|
Days
|
= (V02 / V01) * 1
|
Equipment Operator
|
Days
|
= (V02 / V01) * 3
|
Note: "1" and "3" multipliers shown in formulas above indicate the number of workers. Average Work Hours are used in the Labor Conversion factor which is not shown here.
Equipment Components
Estimate Item Description
|
Units
|
Formula
|
54" Smooth Drum Vibratory Roller
|
Days
|
= (V02 / V01) * 2
|
2200 Gallon Water Truck
|
Days
|
= (V02 / V01) * 1
|
Note: "1" and "2" multipliers shown in formulas above indicate the pieces of equipment. Average Operating Hours are used in the Equipment Conversion factor which is not shown here.