Crew examples

Crew in the cost database

  • Crew description:

    Description Daily production Production units
    Compaction crew - Road work 400 CY
  • Labor components:

    Labor description Quantity Hours
    Labor foreman 1 8.0
    Laborer 1 8.0
    Equipment operator 3 8.0
  • Equipment components:

    Equipment description Quantity Hours
    54" smooth drum vibratory roller 2 8.0
    2200 gallon water truck 1 8.0

Crew in an estimate

  • Crew header:

    Estimate assembly description Units Formula
    Compaction crew - Road work Days = (V02 / V01)
  • Formula variables

    Variable Variable description Units
    V01 Average daily production quantity CY
    V02 Total quantity CY
    When Crews are added to an estimate, variables and formulas are automatically generated based on the daily production quantity and the number of workers and equipment.
  • Labor components

    Estimate item description Units Formula
    Labor foreman Days = (V02 / V01) * 1
    Laborer Days = (V02 / V01) * 1
    Equipment operator Days = (V02 / V01) * 3
    In the formulas above, the 1 and 3 multipliers indicate the number of workers. Average work hours are used to calculate the labor conversion factor, though that calculation is not shown here.
  • Equipment components

    Estimate item description Units Formula
    54" smooth drum vibratory roller Days = (V02 / V01) * 2
    2200 gallon water truck Days = (V02 / V01) * 1
    In the formulas above, the 1 and 3 multipliers indicate the pieces of equipment. Average operating hours are used to calculate the equipment conversion factor, though that calculation is not shown here.