Crew Example In Estimate Cost Database
Crew Description
| Description | Daily Production | Prod. Units |
| Compaction Crew - Road Work | 400 | CY |
Labor Components
| Labor Description | Quantity | Hours |
| Labor Foreman | 1 | 8.0 |
| Laborer | 1 | 8.0 |
| Equipment Operator | 3 | 8.0 |
Equipment Components
| Equipment Description | Quantity | Hours |
| 54" Smooth Drum Vibratory Roller | 2 | 8.0 |
| 2200 Gallon Water Truck | 1 | 8.0 |
Same Crew Example When Added To An Estimate
Crew Header
| Estimate Assembly Description | Units | Formula |
| Compaction Crew - Road Work | Days | = (V02 / V01) |
Formula Variables
| Variable | Variable Description | Units |
| V01 | Average Daily Production Quantity | CY |
| V02 | Total Quantity | CY |
Note: When Crews are added to an estimate, variables and formulas are auto-generated using the daily production quantity and number of workers and pieces of equipment.
Labor Components
| Estimate Item Description | Units | Formula |
| Labor Foreman | Days | = (V02 / V01) * 1 |
| Laborer | Days | = (V02 / V01) * 1 |
| Equipment Operator | Days | = (V02 / V01) * 3 |
Note: "1" and "3" multipliers shown in formulas above indicate the number of workers. Average Work Hours are used in the Labor Conversion factor which is not shown here.
Equipment Components
| Estimate Item Description | Units | Formula |
| 54" Smooth Drum Vibratory Roller | Days | = (V02 / V01) * 2 |
| 2200 Gallon Water Truck | Days | = (V02 / V01) * 1 |
Note: "1" and "2" multipliers shown in formulas above indicate the pieces of equipment. Average Operating Hours are used in the Equipment Conversion factor which is not shown here.