Import items from another estimate
- Go to Leads or Projects and select the lead or project in the Quick Select section.
- On the Lead or Project Home page, select Estimates in the Preconstruction section.
- Select the estimate number or title from the list.
- Select View Estimate.
- Within the estimate, select the Items tab.
- Select Add / Import or the plus sign (+) on a particular cost code section and select Import From Other Estimate.
- In the Target Cost Code and Location section, do the following:
- Select one of the following options:
- Select Use Existing Cost Code and select or update the cost code.
- Select Import Cost Code from Source Estimate.
- Optionally, if locations have been enabled for the estimate, select the target Location from the dropdown.
- Select one of the following options:
- In the Source Estimate section, do the following:
- Select Lead or Project from the dropdown.
- Select the source lead or project number from the dropdown.
- Select the source estimate number from the dropdown.
- Select the cost code from the dropdown.
- In the Estimate Items to Import section, do the following:
- Optionally, use the Search field to filter the list.
- Select one or more items from the list.
- Select Add & Close.
The source item quantity is copied to the target estimate, so estimators must review all imported items for accuracy.