Import submittals using an Excel file

You can save time and import submittals by uploading a Microsoft Excel file.

Prepare an Excel file for import

  1. Open a blank Microsoft Excel spreadsheet or download the sample file.
  2. Label the first row with the column names shown in the table below.

    Make sure that all the required fields are included. Field names do not contain any spacing within the word, or before and after.

    Make sure that the sheet is labeled as Sheet1.

  3. Enter your data starting from the second row.

  4. Save the file in Excel 97-2003 format (*.xls).
  5. Close the file to enable Sage Construction Management to import the data.

Import the file

  1. Go to Leads or Projects and select the lead or project in the Quick Select section.
  2. On the Lead or Project Home page, select Submittals in the Correspondence section.
  3. Select Actions > Import From Excel.
  4. Select Choose File and find the file on your local drive.

    The data will be imported automatically.

Microsoft Excel import sample

Download the submittals sample file.

Submittal file fields

Column name / First row Required (*) Field type Comments
ProjectNumber * Text Must be 25 characters or fewer.
PrimeContractNumber Text Must be 25 characters or fewer.
SubmittalNumber * Text Must be 25 characters or fewer.
SubmittalDate * Date
  • Recommended date format: DD-MMM-YYYY

    For example, 15-Oct-2023.

  • US supported format: MM-DD-YYYY

    For example, 10/15/2023.

  • ISO supported format: YYYY-MM-DD

    For example, 2023-10-15.

SubmittalSubject * Text
SubmittalDescription * Text
SubmittalOriginatorCompany * Text The originator company (for example, the subcontractor or the supplier) must already exist in Sage Construction Management before importing the file.
SubmittalOriginatorContact Text The originator contact must already exist in Sage Construction Management before importing the file, and must match the contact's display name.
SubmittalCoordinatorCompany * Text The coordinator company (for example, the general contractor) must already exist in Sage Construction Management before importing the file.
SubmittalCoordinatorContact Text The coordinator contact must already exist in Sage Construction Management before importing the file, and must match the contact's display name.
SubmittalItemNumber Numeric

If a submittal contains multiple submittal items, add one line for each item.

If a submittal item is imported, then the SubmittalItemNumber, SubmittalItemDescription, SubmittalItemQuantity, and SubmittalItemUnit fields are required.

The value under the SubmittalItemStatus column must match one of the options specified in Settings () > Feature Settings > Correspondence > Submittal Item Status.

SubmittalItemDescription Text
SubmittalItemQuantity Numeric
SubmittalItemUnit Text
SubmittalItemManufacturer Text
SubmittalItemManufacturerCatalogNumber Text
SubmittalItemUPC Text
SubmittalItemRefPrimeContract Text
SubmittalItemRefCO Text
SubmittalItemRefSubcontract Text
SubmittalItemRefSCO Text
SubmittalItemRefDrawing Text
SubmittalItemRefLocation Text
SubmittalItemRefSpecSection Text
SubmittalItemRefOther Text
SubmittalItemDueFromOriginator Date
SubmittalItemReceivedFromOriginator   Date
SubmittalItemRequiredOnSiteDate   Date
SubmittalItemAnticipatedDeliveryDate   Date
SubmittalItemEstimatedDeliveryDate   Date
SubmittalItemActualDeliveryDate   Date
SubmittalItemStatus   Text
SubmittalItemStatusDate   Date
SubmittalItemLeadTime   Numeric
SubmittalItemDesignReviewTime   Numeric
SubmittalItemInternalReviewTime   Numeric