Import Work Items Into Contract Admin, Procurement, or Work Order Transactions
Prerequisite For Importing Work Items
- With exception for Anticipated Costs, the "Target" Contract Admin, Procurement, or Work Order transaction must be saved.
- Job Cost Codes must exist for the project.
Import Data Entry Steps
- Click the 'Add / Import Items' from the drop-down as follows:
- Anticipated Costs: See Actions drop-down on Procurement Landing Page or at the top right of Anticipated Costs listing.
- RFP Packages: See drop-down above the Bidders list.
- Contract Admin | Procurement | Work Order Transactions: See drop-down above Items grid.
- Click 'Import Work Items' option in the drop-down. This will refresh the page.
- Select the Filter Method: Text Search or Classification System (eg. Master Cost Code Structure, CSI Codes).
- If a Classification System is selected, click the lookup icon to select a classification code otherwise enter text to search.
- Select the rate to be imported. Options are shown below.
- Total Cost Rate
- Total Sell Rate (eg. Proposal Rate)
- Material Cost Rate
- Material Sell Rate
- Labor Base Cost Rate
- Labor Cost Rate (eg. Base + Burden Cost Rate)
- Labor Sell Rate
- Equipment Base Cost Rate
- Equipment Cost Rate (eg. Base + Burden Cost Rate)
- Equipment Sell Rate
- Sub Cost Rate
- Sub Sell Rate
- Other Cost Rate
- Other Sell Rate
- Click the Filter button and wait until items appear in the grid below.
- Select the item(s) in the list by clicking the checkbox.
- Enter a quantity for each selected item.
- Optional: Select a Cost Code for each item being imported. If left blank, the default will be used.
- Select the default Job Cost Code below the grid. This is required when importing.
- Select the Resource Type: Materials (M), Labor (L), Equipment (E), Sub (S) and Other (O).
Note: Resource Type is only applicable when importing items into POs, Bills or Misc. Expenses. - Click the 'Add' or 'Add and Close' button.