Edit job cost code values for anticipated costs

  1. Go to Projects and select the appropriate project in the Quick Select section.
  2. On the Project Home page, select Anticipated Costs in the Procurement section.
  3. Select Edit.
  4. For each job cost code, update the cost of each resource, such as materials, labor, and so on, as needed.

  5. Select Save & Close.