Import job cost codes into anticipated costs

  1. Go to Projects and select the appropriate project in the Quick Select section.
  2. On the Project Home page, select Anticipated Costs in the Procurement section.
  3. Select Actions > Import Job Cost Codes.
  4. Optionally, use the Search field to filter the list.
  5. Select one or more job cost codes from the list.
  6. For each job cost code, enter the corresponding dollar amount for the following costs.

    1. M Cost for materials
    2. L Cost for labor
    3. E Cost for equipment
    4. S Cost for subcontract
    5. O Cost for other
  7. Optionally, select the prime contract from the dropdown.

    The prime contract must be approved with a status date.

  8. Select Add & Close.

The added job cost codes appear on the Anticipated Costs – Summary by Job Cost Code and Resource Type page.