Import job cost codes into anticipated costs
- Select Projects and select the required project.
- On the Project Home menu, under Procurement, select Anticipated Costs.
- Select Actions > Import Job Cost Codes.
- Optionally, enter text in the search field to filter the Job Cost Code listing.
The search box displays only if there are more than ten (10) cost codes. - Select the checkboxes for the required Job Cost Codes.
- Select the Prime Contract from the dropdown.
- Select the Resource Type from the dropdown:
- M (Materials )
- L (Labor)
- E (Equipment )
- S (Sub)
- O (Other )
- Select Add and Close.
The added job cost codes display in the Anticipated Costs - Itemized Breakdown page.