Create a purchase order change order (PO CO) manually
- Go to Projects and select the appropriate project in the Quick Select section.
- On the Project Home page, select PO COs in the Procurement section.
- Select Actions > Add PO CO.
-
Optionally, update the Project.
-
Select the Prime Contract.
-
Select the Supplier Company and the PO.
-
Select Next.
- Optionally, in the PO Lines section, select the PO items that have a change to be included in the PO CO and enter the Quantity.
-
Optionally, update the PO CO # and the Order Number as needed.
Sage Construction Management automatically assigns the next number in sequence, based on the existing records and the default format.
-
Optionally, update the Issue Date and Subject as needed.
By default, the issue date is set to today's date and the subject is set to the selected PO's subject.
-
Optionally, select the PO CO Type.
-
Update the Status, if needed.
By default the status is set to Pending.
-
Optionally, select Link Related PO Files.
-
Select Finish.