Create a PO CO manually
- Go to Projects and select the project in the Quick Select section.
- On the Project Home page, select PO COs in the Procurement section.
- Select Actions > Add PO CO.
-
Optionally, update the Project or Prime Contract.
-
Select the Supplier Company and the PO.
-
In the PO Lines section, select the PO items that have a change to be included in the PO CO and enter the Quantity.
-
Enter the PO CO #.
-
Optionally, update the Order Number, Issue Date, or Subject as needed.
By default, the issue date is set to today's date and the subject is set to the selected PO's subject.
-
Optionally, select the PO CO Type.
-
Update the Status, if needed.
By default the status is set to Pending.
-
Optionally, select Link Related PO Files.
-
Select Finish.