Lock or unlock a purchase order (PO)
Before you begin
-
Log in to Sage Construction Management as an administrator.
Lock or unlock a bill manually
- Go to Projects and select the appropriate project in the Quick Select section.
- On the Project Home page, select POs in the Procurement section.
- Select the PO number from the list to open the PO Information page.
- In the Approval and Lock Status section, do the following:
- To lock the PO, select the Locked checkbox.
- To unlock the PO, clear the Locked checkbox.
- In the dialog, select OK to confirm your action.