Add a subcontract, purchase order (PO), or subcontract change order (SCO) from a change order (CO)
- 
                                                        
Go to Projects and select the appropriate project in the Quick Select section.
 - 
                                                        
On the Project Home page, select PO, Subcontract, or SCO in the Procurement section.
 - Select Actions > Add From CO.
 - Optionally, update the Project or Prime Contract number.
 - Select the Supplier / Subcontractor Company.
 - Select the type of transaction to be created, PO, Subcontract, or SCO.
The SCO option is only available if a subcontract has already been issued to the vendor.
 - Select the change orders from the list to be included in the PO, Subcontract, or SCO.
 - Select Next.
 - Optionally, update the PO, Subcontract, or SCO #.
By default, Sage Construction Management automatically assigns the next available PO, subcontract, or SCO number.
 - Optionally, update the Issue Date as needed.
The default value is today's date.
 - Enter a Subject.
 - Optionally, select the Supplier or Subcontractor Contact.
 - If you are creating a subcontract, optionally, select the Subcontract Type.
 - Optionally, update the Status.
The default value is Pending, but you can change it later, unless a transaction workflow is in place.
 - Optionally, update the Status Date.
 - To use the default AP tax code, keep the corresponding option selected.
 - Optionally, select Link Related Files to link the CO related files to the new transaction.
 - Select Finish.