Copy a subcontract
Step 1: Specify the source subcontract
- Go to Projects and select the appropriate project in the Quick Select section.
- On the Project Home page, select Subcontracts in the Procurement section.
- Select Actions > Copy Subcontract.
- Optionally, update the Project number as needed.
- Select the Prime Contract.
- Select the Subcontractor Company and Subcontract #.
- Select Next.
Step 2: Specify the subcontract items and new subcontract information
- In the Subcontract Lines section, select one or more items as needed.
- In the New Subcontract Information section, do the following:
- Select the target Project and Prime Contract.
- Optionally, update the Subcontract # as needed.
Sage Construction Management automatically assigns the next number in sequence, based on the existing records and the default format.
- Optionally, update the Issue Date.
The default value is today's date.
- Optionally, update the Subcontract Type as needed.
By default, this field is set to the type of the original subcontract.
- Enter the Subject.
- Select the Subcontract Status.
- Update the Status Date.
The default value is today's date.
- Select Finish.