Add tasks and child tasks to a schedule
Add tasks at the bottom of the schedule
- Go to Projects and select the appropriate project in the Quick Select section.
- On the Project Home page, select Scheduling Overview or Schedules in the Scheduling section.
- In the Schedules (Gantt Chart) section, select the appropriate schedule.
- Select the Add new row icon (
) on the toolbar .
- Enter the Task description in the new row added at the bottom of the table.
- Select a Start date.
The start date is required before entering a duration.
- Enter the duration in Days.
The end date is automatically set based on the start date and duration.
- Optionally, enter a Completion percentage if the task has already started.
For example, enter 10 for 10 %.
- Optionally, enter a Predecessor task.
- Select the Submit changes to server icon (
) on the toolbar.
Add tasks between existing tasks
- Go to Projects and select the appropriate project in the Quick Select section.
- On the Project Home page, select Scheduling Overview or Schedules in the Scheduling section.
- In the Schedules (Gantt Chart) section, select the appropriate schedule.
- Select the task before which the new task needs to be added.
- Select the Add new row icon (
) on the toolbar and select Add new empty row above in the dropdown.
- Enter the Task description.
- Select a Start date.
The start date is required before entering a duration.
- Enter the duration in Days.
The end date is automatically set based on the start date and duration.
- Optionally, enter a Completion percentage if the task has already started.
For example, enter 10 for 10 %.
- Optionally, enter a Predecessor task.
- Select the Submit changes to server icon (
) on the toolbar.
Add child tasks
- Go to Projects and select the appropriate project in the Quick Select section.
- On the Project Home page, select Scheduling Overview or Schedules in the Scheduling section.
- In the Schedules (Gantt Chart) section, select the appropriate schedule.
- Select the parent task.
- Select the Add new child row icon (
) on the toolbar .
- Enter the Task description.
- Select a Start date.
- Enter the duration in Days.
The end date is automatically set based on the start date and duration.
- Optionally, enter a Completion percentage if the task has already started.
For example, enter 10 for 10 %.
- Optionally, enter a Predecessor task.
- Select the Submit changes to server icon (
) on the toolbar.
Predecessor reference examples
Predecessor task ID = 19:
- FS with lag 0: 19
- FS with lag 2: 19+2
- SS with lag 3: 19SS+3
- FF with lag 1: 19FF+1