Reset the baseline dates for all tasks
Before you begin
-
Save any changes that were made manually to the schedule.
Reset the baseline dates
- Go to Projects and select the appropriate project in the Quick Select section.
- On the Project Home page, select Scheduling Overview or Schedules in the Scheduling section.
- In the Schedules (Gantt Chart) section, select the appropriate schedule.
- Select one or more tasks from the list as needed.The baseline dates will be reset for all tasks, not just the ones that you select.
- Select Choose Bulk Actions on the toolbar.
- Select Reset Baseline Dates to Scheduled Dates for all tasks.
- Select Apply. Sage Construction Management will automatically copy the start and end date to the baseline dates for all tasks.
Next step: Select Show Baseline Dates on the toolbar to view the Baseline Start, Baseline Days, and Baseline End columns in the table.