Reset the baseline dates for all tasks

Before you begin

  • Save any changes that were made manually to the schedule.


Reset the baseline dates

  1. Go to Projects and select the appropriate project in the Quick Select section.
  2. On the Project Home page, select Scheduling Overview or Schedules in the Scheduling section.
  3. In the Schedules (Gantt Chart) section, select the appropriate schedule.
  4. Select one or more tasks from the list as needed.
    The baseline dates will be reset for all tasks, not just the ones that you select.
  5. Select Choose Bulk Actions on the toolbar.
  6. Select Reset Baseline Dates to Scheduled Dates for all tasks.
  7. Select Apply. Sage Construction Management will automatically copy the start and end date to the baseline dates for all tasks.

Next step: Select Show Baseline Dates on the toolbar to view the Baseline Start, Baseline Days, and Baseline End columns in the table.