Set the prime contract dates based on the schedule dates
Before you begin
-
Save any changes that were made manually to the schedule.
Set the prime contract dates
- Go to Projects and select the appropriate project in the Quick Select section.
- On the Project Home page, select Scheduling Overview or Schedules in the Scheduling section.
- In the Schedules (Gantt Chart) section, select the appropriate schedule.
- Select one or more tasks from the list as needed.
- Select Choose Bulk Actions on the toolbar.
- Select the following options as needed:
- Set the Prime Contract's Estimated Start and Estimated Finish dates based on the Schedule dates.
- Set the Prime Contract's Actual Start and Actual Finish dates based on the Schedule dates.
- Select Apply.