Set the prime contract dates based on the schedule dates

Before you begin

  • Save any changes that were made manually to the schedule.


Set the prime contract dates

  1. Go to Projects and select the appropriate project in the Quick Select section.
  2. On the Project Home page, select Scheduling Overview or Schedules in the Scheduling section.
  3. In the Schedules (Gantt Chart) section, select the appropriate schedule.
  4. Select one or more tasks from the list as needed.
  5. Select Choose Bulk Actions on the toolbar.
  6. Select the following options as needed:
    • Set the Prime Contract's Estimated Start and Estimated Finish dates based on the Schedule dates.
    • Set the Prime Contract's Actual Start and Actual Finish dates based on the Schedule dates.
  7. Select Apply.