Scheduling Functions - Global Changes - Update Percent Complete
Before using the Global Change function, the schedule should be saved if changes were made manually.
Relevant Icons on Toolbar

Update Percent Complete for one or more Tasks
- In the Gantt Chart listing, select one or more task using the circular checkbox on the left.
- Click the 'Global Changes' button
on the Toolbar.
- Check the 'Percent Complete' option.
- Enter a Percentage (10% = 10).
- Click the 'Save' button. This will automatically update and save selected tasks. In addition, Gantt Chart will be refreshed showing these changes.