Print or export a look ahead schedule

  1. Go to Projects and select the appropriate project in the Quick Select section.
  2. On the Project Home page, select Schedules in the Scheduling section.
  3. In the Schedules (Gantt Chart) section, select the appropriate schedule's record number or name.
  4. Select Filter Tasks () on the toolbar.
  5. In the dialog, do the following:
    1. Select Look Ahead and enter the number of weeks in the available field.

      For example, enter 4 to filter the schedule for the next 4 weeks.

    2. Optionally, select the Include In Progress Tasks checkbox.
    3. Select Apply.
  6. Select the Print grid icon () or the Print grid to Adobe PDF icon () button on the toolbar.
  7. In the dialog, review the paper size and format options, then select OK.