Copy project to-dos

  1. Go to Projects and select the appropriate project from the list.
  2. On the Project Home page, select Schedules in the Scheduling section.
  3. In the General and Project To Dos section, select Actions > Copy Project To Do.
  4. In the Source Project section, select the source Project.
  5. In the Project To Dos section, select the to-dos to be copied.
  6. In the Target Project section, select the target Project and, optionally, the Due Date.

    The target project must be different from the source project.

  7. Select Copy.
    The status of all copied project to-dos is set to Not Started.