Add workforce to a daily log

The Workforce section displays all labor resources, including subcontractors and consultants, who worked on the project that day. As with equipment entries, each workforce record must include the company, number of workers, and work hours.

Open the daily log details

  1. Go to Projects and select the appropriate project in the Quick Select section.
  2. On the Project Home page, select Daily Logs in the Documentation section.
  3. On the Daily Logs page, select the appropriate date from the list.

Add workforce manually

  1. In the Workforce (All Trades) section, select Add / Import Items > Add Manually.
  2. Select the Company from the dropdown.

    Typically, this is either your firm or a subcontractor.

  3. Optionally, select the magnifying glass icon () next to the Labor Type / Code field and select the appropriate labor type in the dialog.

    The labor type codes and descriptions in the dialog are populated from the labor items in the cost database.

  4. Enter the number of workers for the selected company, labor type, and day in the Quantity field.
  5. Enter the work Hours per worker.

    The Total Hours equal the quantity multiplied by the work hours.

  6. Optionally, enter any Comments.
  7. Select Add & Close.

Add workforce from the project directory

  1. In the Workforce (All Trades) section, select Add / Import Items > Add Workforce Using Project Directory.
  2. Optionally, use the Search field to filter the list.
  3. Select one or more companies from the list.
  4. For each selected company, enter the number of workers in the Quantity field and the average work Hours per worker.

    The total hours equal the quantity multiplied by the work hours.

  5. Select Add & Close.

Import workforce

  1. In the Workforce (All Trades) section, select Add / Import Items.

  2. Select one of the following options: