Copy a schedule
- Go to Projects and select the appropriate project in the Quick Select section.
- On the Project Home page, select Schedules in the Scheduling section.
- In the Schedules (Gantt Chart) section, select Actions > Copy Schedule.
- Optionally, update the Project number as needed.
- Optionally, select the Prime Contract.
- Select the Schedule.
- Select Next.
- Select the Project number to which the schedule will be copied.
- Optionally, select the Prime Contract.
For design-build firms, developers, and homebuilders, this field is recommended if there are going to be multiple lots or contracts.
- Optionally, update the Schedule #, such as 001.
- Enter the Description.
- Select the work Calendar which will determine the work days and holidays.Admins can specify the calendars in Settings (