New column in importing job cost codes for anticipated costs

The difference between the Cost Budget and the sum of Cost To Date, Commitments, and Anticipated Costs displays now in a separate column in the Cost Analysis section of the Anticipated Costs.

Details

To view the new variance column with the cost budget differences, go to the Project Home of the selected project and click Anticipated Costs from the Procurement section.

The Cost Analysis displays including the Cost Budget - (CTD. + Comm. + Ant.) column that shows the difference between the Cost Budget and the sum of Cost To Date + Comm. + Ant displays for the job cost codes with the imported unit prices.

The new column with the difference between the cost budget and the sum of the CTD + Comm. + Ant.

Permissions and other requirements

  • Job Cost Codes must exist for the project.