Add a subcontract change order (SCO) manually

Add the SCO header information

  1. Go to Projects and select the appropriate project in the Quick Select section.
  2. On the Project Home page, select SCOs in the Procurement section.
  3. Select Actions > Add Manually.
  4. Optionally, update the Project number as needed.
  5. Select the Prime Contract.
  6. Optionally, add the CO #, WO #, or both.

  7. Select the Subcontract from the dropdown.
  8. In the General SCO Information section, do the following:
    • Optionally, update the Issue Date.

      The default value is today's date.

    • Optionally, update the Order Number as needed.

      This field is required.

      The SCO order number determines the previous SCO amounts.
    • Optionally, update the SCO # as needed.

      This field is required.

    • Optionally, select the appropriate Initiated By option from the dropdown.
    • Enter the SCO Subject.

      This field is required.

    • Optionally, update the SCO Status as needed.

    • Optionally, update the Status Date.

      The default value is today's date.

    The order number and SCO number are set automatically based on the selected subcontract.
  9. Optionally, in the Subcontractor Company Information section, update the Contact and Company Address if needed.

    The Company field cannot be edited.

    The subcontractor company information is set automatically based on the selected subcontract.
  10. Optionally, in the Prime Contractor Company Information section, update the Contact and Company Address if needed.

    The Company field cannot be edited.

    The prime contractor company information is set automatically based on the selected subcontract.
  11. Optionally, enter the Scope of Work.
  12. Optionally, in the References section, do the following:
    • Select a Drawing.
    • Enter a Location.
    • Select an RFI #.
    • Enter the Spec. Section.
    • Enter Other information as needed.
  13. Optionally, in the Schedule Impact section, do the following:
    • If a scheduling delay cannot be determined yet, select the To Be Determined Later checkbox.
    • Enter the number of work Days to add to or remove from the subcontractor’s schedule due to this SCO.

      If the To Be Determined Later checkbox is selected, leave this field set to zero.

Optional: Set default values for the SCO items

  1. In the Default Line Item Values section, select the default Job Cost Code, Tax Code, or both.

    These default values are applied to the items when those fields are left blank.

Optional: Add SCO items manually

  1. In the SCO Line Items section, do the following for each item:
    1. Enter the Item #, Description, and Quantity.

      The item number determines the sorting order.

    2. Enter the Unit Price and, optionally, the Units.
    3. Optionally, select the Cost Code.

      If a job cost code is not selected, the default cost code specified in the Default Line Item Values section will be used.

    4. Optionally, select a Tax code.

      If a tax code is not selected and a default tax code specified in the Default Line Item Values section, the default will be used.

    If the subcontract type is Unit Price and this is a new billing item, the quantity represents the estimated project quantity.
  2. Select Save.

Optional: Import SCO items

  1. In the SCO Line Items section, select Add / Import Items.
  2. Select one of the following options: