Submittals overview

Submittals are items documented in project specifications that need to be provided to the project owner, architect, or construction management firm for review and approval. Some examples of submittals are shop drawings, engineering data, material samples, test results, and product literature. Certain submittals such as product manuals are often used later by the client for operational purposes.

In the case of a general contractor (GC), submittals are requested first from subcontractors and suppliers according to the project specifications. They’re then submitted to the respondent for review and approval. Occasionally, rejected items will need to be resubmitted, which might require creating a new submittal. After final approval is granted, the GC will return the approved submittal and related documentation to the suppliers and subcontractors, so that materials can be purchased.

Submittal functions

Requesting submittal details

Submittal response functions

After receiving the responses to the submittal items, make sure to review and update the status for each item.

If a submittal has only one respondent, the item status can be updated in the TeamLink Portal. If there are multiple respondents, the item status is disabled in the portal to prevent confusion and overwriting by different external team members.