Implementation Tips For Unit Price Estimating And Contracts
In the Heavy Highway and Utility construction market, Unit Price estimating and contracts are very common because for these types of projects it is difficult to establish precise quantities of materials or equipment time needed. If the design team or client (ex. government organization) does provide estimated quantities then they are often used for reference purposes only. The actual contract cost will not be determined until project completion when all invoices have been submitted for the placed or excavated quantities.
Business Scenario
- Estimate and Contract Type: Unit Price
- Unit Price or Bid Items: 3 Separate Fence Types
1. Implementation Plan: Contact Management
Make sure all firms involved on the project including the client are added in the Contact Management module.
Example Firms:
- Client
- Architect
- Suppliers
- Subcontractors
Related Help Topic:
2. Implementation Plan: Project
Create the Project.
Related Help Topics:
3. Implementation Plan: Estimates
Create estimates where bid items are used as the Work Breakdown Structure (WBS) Divisions.
Related Help Topic:
Estimate Work Breakdown Structure (WBS)—Set To Bid or Pay Items:
An estimate is organized into cost code sections that have internal grouping fields such as division and major. For Unit Price estimating, cost codes should represent Unit Price Bid Items. There can also be sub-sections (ex. Cost Code Internal Major) to represent the various elements of each Bid Item as shown in Option B.
Option A: Using Cost Code Only | Option B: Using Cost Code and Internal Grouping Fields | |
|
|
4. Implementation Plan: Project Directory
The following companies should be added to the Project Directory.
- Client
- Architect
- Your Firm
- Suppliers
- Subcontractors
Related Help Topic:
5. Implementation Plan: Job Cost Codes, Prime Contract and Original Budgets
The Estimated prepared in Sage Construction Management can be used by the Contract Admin Setup Wizard to cretate Job Cost Codes, Prime Contract, and Budgets. As an alternative to using a Sage Construction Management estimate, a spreadsheet could also be prepared that lists the bid items, unit price, and internal cost budgets.
Related Help Topics:
- Help Topic - Contract Setup Wizard
- Help Topic - Job Cost Codes Overview
- Help Topic - Prime Contract Overview
Example Unit Price Contract Import Files (Alternative to using Sage Construction Management Estimate):
Project / Prime Contract / Procurement Structure
- Project
- Prime Contract # 001 : All Phases Of Construction
- PO or Subcontract # 001 : Vendor 1
- PO or Subcontract # 002 : Vendor 2
- PO or Subcontract # 003 : Vendor 3
- Labor Timecards
- Equipment Timecards
- Prime Contract # 001 : All Phases Of Construction
Job Cost Code Structure
Although Estimates can have a 2-tiered work breakdown structure as shown in option B above, job cost codes for the project management phase should only reflect the Bid Items. Thus, the WBS Divisions will become the job cost codes in either case. This is a requirement for the unit price specific financial dashboards.
Job Cost Code (JCC) | JCC Description | JCC Qty | JCC Unit |
01 | Bid Item #1 Description | Est. Bid Item Qty | Est. Bid Item Units |
02 | Bid Item #2 Description | Est. Bid Item Qty | Est. Bid Item Units |
03 | Bid Item #3 Description | Est. Bid Item Qty | Est. Bid Item Units |
6. Implementation Plan: Documenting Placed or Excavated Quantities
Unit Price Items referenced in the Prime Contract can be imported into Daily Logs so placed or excavated quantities can be documented. These entries are then summarized in the Unit Price Financial Dashboard that is shown below.
Related Help Topic:
7. Implementation Plan: POs and/or Subcontracts
Issue POs and Subcontracts for materials, equipment rental, and services required for the project.
Related Help Topic:
8. Implementation Plan: Enter and Approve Labor Timecards
Related Help Topics:
- Help Topic - Labor Timecards
- Help Topic - Adding Labor Timecards - Daily
- Help Topic - Adding Labor Timecards - Weekly
- Help Topic - Adding Crew Timecards - Daily
- Help Topic - Import Timecards From Microsoft Excel
- Help Topic - Approving Labor Timecards
9. Implementation Plan: Prepare Client/Prime Contract Invoice
Prepare one or more progress invoices.
Related Help Topics:
10. Implementation Plan: Review Standard Job Cost Dashboards in Project Analytics
In Project Analytics, there are dashboards available to show financials rolled up by prime contract and by job cost code for cost tracking.
Related Help Topic:
See also
General Guidelines for Creating COs for Unit Price Contracts