Subcontract invoices overview
Progress payments for subcontracts are processed in the Subcontract Invoice feature. Preparing subcontract invoices can be complex and time-consuming due to retainage (holdbacks), change order tracking, and prior billing calculations. Sage Construction Management provides wizards to streamline this process and significantly reduce effort.
-
When you create or modify a subcontract invoice, Sage Construction Management checks the vendor’s profile for expired insurance records and displays a warning message in red if any are found.
-
The subcontract invoice process varies by contract type. Learn more about the subcontract invoice billing methods.
-
The subcontract invoice order number (not the invoice date or subcontract invoice number) determines previous invoice amounts. Sage Construction Management automatically assigns the next order number when you create a subcontract invoice.
Invoice date Order number Invoice number 31-Mar-2017 1 001 30-Apr-2017 2 002 15-May-2017 * 3 003 15-May-2017 * 4 004 * You can create multiple invoices on the same date, but ensure each one references the correct order number.
-
Default retainage percentages for work and stored materials are copied from the subcontract but can be updated on the subcontract invoice.
-
Previous, current, and billed retainage amounts are tracked by job cost code, not at the item level, such as Schedule of Values, subcontract change order (SCO) items, or cost plus items.
-
Always process billed retainage last. For example, if both Schedule of Values and retainage are billed, enter retainage after all other amounts.
-
You cannot change the project number after saving a subcontract invoice. If it's incorrect, delete and recreate the transaction.
-
Only subcontract invoices marked as approved appear in project analytics and can be exported using an AccountingLink utility.
-
When a subcontract invoice is exported using AccountingLink, subcontract invoices can be automatically locked to prevent further changes or deletion.
-
When a subcontract invoice is created in the TeamLink portal, email notifications are sent based on the following order of precedence:
-
PM Contact on the prime contract or subcontract (internal Sage Construction Management user).
-
If not specified, PM Contact in the Internal Stakeholders section of the General Project Information page.
-
If still not specified, the first Administrator.
If a contact is not defined at one level, Sage Construction Management moves to the next available option.
-
- Ensure that the subcontract exists and is approved with a status date.
- Set up the job cost codes. They're required for subcontract Schedule of Values, unit price items, SCO items, cost plus entries, and billed retainage (holdbacks).
- Optionally, set up the sales tax codes, which can be applied to cost plus entries and billed retainage (holdbacks).
-
Review recent subcontract change orders (SCOs) to ensure they are approved and have a status date earlier than the planned subcontract invoice issue date.
Add subcontract invoices
- Add a subcontract invoice for a Fixed Lump Sum subcontract
- Add a subcontract invoice for a Cost Plus subcontract
- Add a subcontract invoice for a Unit Price subcontract
Edit subcontract invoices
-
If a workflow rule applies to the subcontract invoice and has already been initiated or approved, you cannot make changes unless you abandon the rule.
-
If the subcontract invoice has been included in a cost plus prime invoice, you cannot make changes unless you remove it from the prime invoice.
-
If the subcontract invoice has been exported and Sage Construction Management is configure to lock transactions automatically in Settings (
) > Company settings > Global settings, only an administrator can temporarily unlock it for non-financial updates.
- Edit a subcontract invoice for a Fixed Lump Sum subcontract
- Edit a subcontract invoice for a Cost Plus subcontract
- Edit a subcontract invoice for a Unit Price subcontract
- Release subcontract invoice retainage
- Edit the tax total for a subcontract invoice
- Lock or unlock a subcontract invoice